Pulls up JKPCC for poor performance, not finalising accounts

The Jammu and Kashmir Projects Construction Corporation (JKPCC) Limited came up for sharp criticism from the Comptroller and Auditor General (CAG) for its poor performance and failure to finalise its accounts amid sharp decline in the value of works from Rs 364.19 crore in 2012-13 to Rs 250.65 crore during 2016-17. The Public Sector Undertaking firm was dependent on the state government departments or agencies for works on nomination basis and had failed to secure any work on competitive tender basis, the CAG said in its report.

JKPCC was incorporated with the objective of execution of construction works for the state and central governments and PSUs, carry on the business of builders, contractors, engineers, architects, surveyors, estimators and designers in J&K and curb monopoly of private contractors and provide healthy competition between private and public sectors. “The company had finalised its accounts up to 2010-11 only. The value of works done decreased from Rs 364.19 crore during 2012-13 to Rs 250.65 crore during 2016-17. It suffered loss of Rs 3.95 crore and Rs 11.69 crore during 2014-15 and 2015-16, respectively,” the report said. It said the shortfall in achievement of targets of value of works done remained between 29 and 50 percent. “Funds ranging between 58.52 percent and 75.55 percent only were utilised on works during 2012-17”.

   

The report said the service tax of Rs 5.14 crore paid in excess had neither been reconciled nor refund thereof received. “The company had not submitted revised cost offers, to the extent of Rs 22.66 crore, to reflect enhanced rate of service tax and made payment of service tax at the enhanced rate without actual recovery of Rs 3.45 crore from the project authorities,” the report said. “The quantum of new works obtained declined during 2012-16 from Rs 349.48 crore to Rs 236.03 crore, but increased during 2016-17 to Rs 696.64 crore. Execution of works in excess of the funds released by the project authorities led to accumulation of outstanding balance of Rs 188 crore as of March 2017 and loss of interest of Rs 26.56 crore,” it said.

The delay in completion of works led to increase in cost to the extent of Rs 360.87 crore which was mainly due to poor monitoring by company and slow progress.

Leave a Reply

Your email address will not be published. Required fields are marked *

2 × 4 =