CEC Kargil reviews pace of developmental works

Chairman and Chief Executive Councillor Kargil Feroz Ahmed Khan Tuesday reviewed the physical and financial progress on developmental works in Silmoo Constituency under Capex Budget Plan, BADP and other centrally sponsored schemes here at a meeting of the concerned officers.

According to an official spokesperson, Executive Engineers of PHE, I&FC, PMGSY and other sectors besides AEEs, AEs, JEs and other concerned officers were present in the meeting. The CEC took brief from the officers about the pace of work on different ongoing projects as well as the proposed works.

   

It was informed in the meeting that work on the construction of link road from Gargardo to Dangal, being constructed at a cost of Rs 194.60 lakh, is in full swing and 90 percent of the project has been completed, while as Rs 25 lakh  has been paid with regard to the construction of link road from Garkone Monastery on account of land and tree compensation.

The officers further informed the CEC that the construction of Foot Bridge at Garkone has been completed at a cost of Rs 120.55 lakhs, while as around 95% repair and construction of Public Health Centre at Batalik and Gargardo has been completed at cost of Rs 28.00 lakhs and 30.00 lakhs respectively. The CEC directed the concerned to prepare proposals for fencing and necessary repairs of the Hostel Block at Higher Secondary School Silmoo so that the completed structure could be used to provide residential facilities to the students of Batalik and other adjoining areas.

Under I&FC sector it was revealed that work on the remodelling of MayourKhul Grong Silmoo is being executed at a cost of Rs 265.00 lakhs while as 75% work on the remodelling of Bari YourbaKhul has been completed for which Rs 271.00 lakhs were sanctioned.