Rambagh flyover: ERA imposes second penalty of Rs 2 crore on contractor for missing deadline

Jammu and Kashmir Economic reconstruction agency (ERA) has imposed a further penalty of Rs two crore on the contractor, M/S Simplex Infrastructure Limited (SIL), executing work on the Jehangir Chowk–Rambagh Flyover.  

A statement by J&K ERA issued on Thursday said M/s SIL has been penalized for its “failure to complete the 2nd Phase of the flyover i.e (Rambagh – Alochibagh stretch).”

   

Chief Executive Officer, J&K ERA Dr. Raghav Langer, in the statement said  that as per the revised time schedule submitted by M/S SIL had to complete the structural portion of 2nd phase of the flyover project by 31st December 2018. 

“However, the same has now got delayed till end of February – 2019 due to sub-optimal manpower, material and machinery deployed by the contractor,” he said.

The Chief Executive Officer said that the strict monitoring of milestones for the mega project is being done on a continuous  basis and the contractor shall be penalized under relevant sections of contract agreement for delaying the work.  

It may be recalled that in the month of October 2018 the contractor has already been penalized with an initial penalty of Rs. 1.25 crore by J&K ERA.

The CEO J&K ERA has also directed the project staff to impose employer’s claims under relevant clauses on the contractor for delays  in the project and additional burden being put on the state exchequer on account of salaries of employees and extension of tenure of the Design and Supervision Consultants deployed on the project by Government.

J&K ERA said that it is constantly engaged with the contractor to ensure that the remaining structural works that include erection of girders, laying of deck slabs, retaining walls, etc. on 3rd phase of the flyover from Alochibagh to Jehangir chowk gets completed as per agreed timelines. 

“It has been reiterated to the contractor to professionally execute the contract agreement or face the brunt of action in future as well,” the statement said. 

The contractor is supposed to make the complete stretch of flyover motorable by June 2019 as per his submitted work plan, it added. 

Leave a Reply

Your email address will not be published. Required fields are marked *

10 + 11 =